• Eng Progress Month of Oct 2025

    Peninsula Worth Hotel, Madinah.

    GANAREL CHECK AND READING
    Electrical total consumption Avg 30 MW,

    Temp Max 44C,

    Occupancy Avg 92%
    Chiller Systems Auto position, Avg 2 units 3 Compressor
    City Water available, water tank full roof tank, B3 tank 73%.
    Generator/ATS/Back up power is position auto, Diesel Laval stander.
    Fire troubles / 12 Troubles > 3 Troubles
    Chlore level %, 0.5 chlorine on test
    Fire pump/Transferring pump auto /Submersible pump is Auto.

    Occupancy Avg 92%
    Chiller Systems Auto position, Avg 2 units 3 Compressor
    City Water available, water tank full roof tank, B3 tank 73%.
    Generator/ATS/Back up power is position auto, Diesel Laval stander.
    Fire troubles / 12 Troubles > 3 Troubles
    Chlore level %, 0.5 chlorine on test
    Fire pump/Transferring pump auto /Submersible pump is Auto.

    Cold/freezing content hot: All cold and freezer units is working good and standard temp.

    Kitchen on operation                    

    Tilting pan #1 Trip, Maintenance Done, Thermostat and overload safety changed.

    Electric ranges Repaired.

    Preventive Maintenance Done, For Fryer pan, Griller hot plate, Combi oven.

    Bakery, Butcher, Cold Kitchen was busy

    Lighting System: All Emr and exit light ok. Authriam Manual operating till Al Fanniya sets program CCMS, Façade light working Manual timing 5.40pm.

    Total Electricity Consumption was 910 MWh

    Total Water Consumption was 6854 units

    Taken last Reading 31/10/2025

    GENERAL WORK

    Total Complaints:

    Electrical 1780

    Plumbing 1274

    AC 1182

    Carpentry 1178

    Paint 380 Rooms Touch up, 38 Ceiling repair paint, Door polishing project Running from 1st floor to 5 Floor.

    From HK, Rec and QMS Compliments Total 1826

    Major Project:  

    • Free sockets in the room for Classification visit Total 55 Rooms.
    • Free Sockets in the bathroom for Classification visit Total 55 Rooms.
    • Liquid dispenser project for quality 490 Rooms 3*490 dispenser.
    • Door polishing project all hotel guest room, (Starting from 1st floor).
    • Windows stickers 55 rooms remains previous project.
    • Evacuation plan (42 Room) Project completed.
    • Room rate plats (42 room) Project completed.
    • Signage updates all hotels for classification visit.
    • Handicap bathroom fix access for classification visit Total 12 Bathrooms.

    Company Work.

    Changed header from Pump room B5. Al Fanniya

    Repair Leakage Riser no 5/6 Al Fanniya

    Change smoke detectors and rectified fire alarms faults total 12 Al Fanniya

    Changed emergency battery from services lift KONE Company.

    Clean grease tank and sewage tank by Aryaf Al Hizaz Company.

    Sheeb Al Jazeera Company make repair floor epoxy from Ramp main car parking entrance

    All Company completed their Monthly visit.

    Challenged Operation.

    Bypass big Shidler sky light.

    Vacuum pit water from services lift.

    Repair supply line from B5 transfer pump

    Repair dish washer machine B1 back area.

    Classification Visit.

    Cristal Visit.

    Upcoming challenge operation.

    Civil Defense Visit.

    Best Regards

    Mohammad Masoud / Maintenance Manager. Eng. Mohammed Al Rushdy / Director of Engineer